Determine the location of the building's internal manhole before starting construction. Then, the engineering office prepares the design drawings for the internal sewage network and submits three copies to the relevant authority for approval of the manhole location that was previously identified.
Connecting the building's internal manhole to the public sewage network.
Granting approval for connecting the electrical power supply by inspecting the building to ensure that the rainwater drainage network is separated from the sewage network. The electricity connection request must first be obtained and approved by the Kuwait Municipality, after which it is submitted to the relevant authority for final approval.